Briefing on 18-ALPHA BESS

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
307 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2028-02-01
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

18-ALPHA BESS is a 307 MW Battery project in Texas, currently active.

SCOUT ENERGY MANAGEMENT, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-02-01.

Queue ID
ERCOT-28INR0328
Location
Cooke, Texas
Technology
Battery
Developer
SCOUT ENERGY MANAGEMENT, LLC
Market / region
ERCOT
Point of interconnection
To the 138 kV Valley View Substation, ( Bus No.691)

What stands out

1

18-ALPHA BESS is a 307 MW Battery project in Texas with status active.

2

SCOUT ENERGY MANAGEMENT, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2028-02-01.

Market and operating context

Queue date
2025-04-21
Proposed COD
2028-02-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

18-ALPHA BESS — verified asset snapshot

FieldValue
Queue IDERCOT-28INR0328
LocationCooke, Texas
TechnologyBattery
DeveloperSCOUT ENERGY MANAGEMENT, LLC
Market / regionERCOT
Point of interconnectionTo the 138 kV Valley View Substation, ( Bus No.691)
Queue date2025-04-21
Proposed COD2028-02-01