WAPA-DSW-2023-G4
225 MW hybrid in Mohave, AZ · In queue since April 2023 · Proposed COD December 2026
225 MW
Capacity
1
Components
Solar
3y 3m
In Queue
—
IA Status
COD target: 2026
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-30
The proposed WAPA-DSW-2023-G4 project is a 225 MW hybrid solar and battery energy storage development in Mohave County, Arizona. The project consists of 225 MW of solar generation. It is located in the West region and is being proposed within the Western Area Power Administration (WAPA) Desert Southwest Region interconnection queue.
The project entered the WAPA-DSW queue on April 24, 2023, with a proposed commercial operation date of December 30, 2026. The point of interconnection (POI) is the White Hills 345-kV Substation. The project's interconnection status is currently listed as active.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
AZ
County
Mohave
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Service Type
—
Point of Interconnection
White Hills 345- kV Substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project WAPA-DSW-2023-G4Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.