WAPA-DSW-2023-G15
500 MW storage in Mohave, AZ · In queue since December 2023 · Proposed COD December 2028
500 MW
Capacity
1
Components
Battery
2y 7m
In Queue
—
IA Status
COD target: 2028
Total Duration
5 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
WAPA-DSW-2023-G15 is a proposed 500 MW battery storage project located in Mohave County, Arizona. The project is in the West region and is being managed within the WAPA Desert Southwest Region interconnection queue, under the queue ID WAPA-DSW-2023-G15. The project entered the queue on December 19, 2023, and has a proposed commercial operation date of December 1, 2028. The point of interconnection is the Mead 230kV Substation.
The project consists of 500 MW of battery storage capacity. As of the latest data, the project's status is listed as active within the interconnection queue. There is no information available regarding an interconnection agreement (IA) status, developer, news coverage, or a link to an existing operating plant.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
AZ
County
Mohave
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Service Type
—
Point of Interconnection
Mead 230kV Substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project WAPA-DSW-2023-G15Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.