TVA-522
67 MW generation in Choctaw, MS · In queue since September 2022 · Proposed COD May 2026
67 MW
Capacity
1
Components
Solar
3y 10m
In Queue
Facility Study
IA Phase
COD target: 2026
Total Duration
3y 8m
Schedule
2 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-05-01
TVA-522 is a proposed solar generation project with a total capacity of 67 MW, located in Choctaw County, Mississippi. The Tennessee Valley Authority (TVA) project entered the TVA interconnection queue on September 23, 2022, and has a proposed commercial operation date of May 1, 2026. Its interconnection point is the Red Hills - Leake 161-kV TL. The project's interconnection status is currently in the Facility Study phase.
The development project consists of 67 MW of solar photovoltaic generation. It is currently listed as an active project within the TVA interconnection queue.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MS
County
Choctaw
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
Red Hills - Leake 161-kV TL
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project TVA-522Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.