TVA-314
60 MW generation in Monroe, MS · In queue since May 2017 · Proposed COD September 2021
60 MW
Capacity
1
Components
Solar
9y 2m
In Queue
IA Executed
IA Phase
COD target: 2021
Total Duration
4y 4m
Schedule
59 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2021-09-15
TVA-314 is a proposed 60 MW solar generation project located in Monroe County, Mississippi. The project is listed in the Tennessee Valley Authority (TVA) interconnection queue with an entry date of May 23, 2017, and a proposed commercial operation date of September 15, 2021. The interconnection agreement for the project has been executed. The point of interconnection is the Stateline - West Point 161-kV transmission line.
The development project is sponsored by TVA. It consists of 60 MW of solar photovoltaic generation capacity. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MS
County
Monroe
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
Stateline - West Point 161-kV TL
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project TVA-314Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.