Project TVA-292 — Project Summary

Queue ID
TVA-292
Capacity
80 MW
Technology
Solar
Status
active
Location
Lake, TN
Region
Southeast
Developer
IA Status
IA Executed

TVA-292

TVA-292BetaActiveSolarTVALBNL

80 MW generation in Lake, TN · In queue since April 2016 · Proposed COD March 2023

BA: TVANERC: SERCRC: TVA

80 MW

Capacity

1

Components

Solar

10y 3m

In Queue

IA Executed

IA Phase

COD target: 2023

Interconnection

Total Duration

6y 11m

Schedule

40 months past proposed COD

Construction75%
Queue EntryApr 19, 2016

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2023-03-31

About

TVA-292 is a proposed 80 MW solar generation project located in Lake County, Tennessee. The project is listed in the Tennessee Valley Authority (TVA) interconnection queue with an entry date of April 19, 2016, and a proposed commercial operation date of March 31, 2023. The interconnection agreement for the project has been executed.

The point of interconnection for TVA-292 is the Highway 412-New Tiptonville 161-kV transmission line. The project consists of 80 MW of solar photovoltaic generation capacity.

Generated from interconnection queue and public data sources

Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TN

County

Lake

Grid Region

Southeast

Market

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Service Type

Point of Interconnection

Highway 412-New Tiptonville 161-kV TL

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
TVA
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.

No Ask reports yet for this entity.

Ask about Project TVA-292
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.