TSGT-GI-TC-2024-08
150 MW generation in Kit Carson, CO · In queue since May 2023 · Proposed COD December 2027
150 MW
Capacity
1
Components
Wind
3y 2m
In Queue
IA Executed
IA Phase
COD target: 2027
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2027-12-31
The proposed wind generation project, identified as TSGT-GI-TC-2024-08, is a 150 MW development in Kit Carson County, Colorado. The project, sponsored by Tri-State Generation and Transmission Association (TSGT), entered the transmission queue on May 26, 2023, and has a proposed commercial operation date of December 27, 2028. The point of interconnection is the Burlington 230kV Substation.
The project's interconnection agreement status is currently listed as "In Progress (unknown study)". Recent news coverage has discussed the project's potential impact on the region's energy infrastructure.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CO
County
Kit Carson
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Service Type
ERIS
Point of Interconnection
Looff 230kV Substation (Burlington Expansion)
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project TSGT-GI-TC-2024-08Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.