TSGT-GI-DISIS-2021-11
300 MW hybrid in Las Animas, CO · In queue since May 2021 · Proposed COD September 2026
300 MW
Capacity
2
Components
Solar + Battery
5y 2m
In Queue
Suspended
IA Phase
COD target: 2026
Total Duration
5y 4m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-05
TSGT-GI-DISIS-2021-11 is a proposed 300 MW hybrid Solar+Battery project located in Las Animas County, Colorado. The project, developed by Tri-State Generation and Transmission Association (TSGT), consists of a 200 MW solar array coupled with a 100 MW battery energy storage system. It is interconnected to the Walsenburg-Gladstone 230kV Line.
The project entered the Tri-State Generation and Transmission Association interconnection queue on May 28, 2021. Its interconnection status is currently listed as "suspended," and its Interconnection Agreement (IA) status is also "suspended." The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk through commissioning — schedule slippage, construction cost overrun, and COD probability vs the stated window. The diligence view that determines whether the project comes online when promised. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CO
County
Las Animas
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Service Type
NRIS
Point of Interconnection
Windowfield 230kV Switching Station
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with curtailment risk decomposed by congestion zone and ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, first-year DSCR, and construction cost overrun exposure — what determines whether the deal clears its covenants once online. Projected across price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project TSGT-GI-DISIS-2021-11Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.