TSGT-GI-DISIS-2021-10
398 MW hybrid in Converse, WY · In queue since May 2021 · Proposed COD June 2023
398 MW
Capacity
2
Components
Solar + Battery
5y 2m
In Queue
Suspended
IA Phase
Signed Jun 2023
Queue → IA
2y 1m
IA → COD
<1 month
Total Duration
2y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 18–30 months
Proposed COD: 2023-06-01
The proposed project TSGT-GI-DISIS-2021-10 is a 398 MW hybrid solar and battery energy storage system located in Converse County, Wyoming. The project, developed by Tri-State Generation and Transmission Association (TSGT), consists of 199 MW of solar photovoltaic generation and 199 MW of battery storage.
The project is currently in the Tri-State Generation and Transmission Association interconnection queue, with an original queue entry date of May 28, 2021. The interconnection agreement status is currently listed as suspended, effective June 1, 2023. The point of interconnection is the DJ-LRS 230kV Line.
Generated from interconnection queue and public data sources
Realization risk through commissioning — schedule slippage, construction cost overrun, and COD probability vs the stated window. The diligence view that determines whether the project comes online when promised. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
WY
County
Converse
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Service Type
NRIS
Point of Interconnection
Hunton Creek 230kV Switching Station
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with curtailment risk decomposed by congestion zone and ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, first-year DSCR, and construction cost overrun exposure — what determines whether the deal clears its covenants once online. Projected across price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project TSGT-GI-DISIS-2021-10Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.