Project TEP-132 — Project Summary

Queue ID
TEP-132
Capacity
150 MW
Technology
Battery
Status
active
Location
Pima, AZ
Region
West
Developer
IA Status

TEP-132

TEP-132BetaActiveBatteryTEPLBNL

150 MW storage in Pima, AZ · In queue since July 2022 · Proposed COD June 2025

BA: AZPSNERC: WECCRC: SPPW

150 MW

Capacity

1

Components

Battery

4 years

In Queue

IA Status

COD target: 2025

Interconnection

Total Duration

2y 11m

Schedule

13 months past proposed COD

Pre-Study0%
Queue EntryJul 14, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-06-02

About

TEP-132 is a proposed 150 MW battery storage project located in Pima County, Arizona. The project, under development by Tucson Electric Power Company (TEP), consists entirely of battery storage. It is currently listed as active in the utility's interconnection queue, with an entry date of July 14, 2022, and a proposed commercial operation date of June 2, 2025. The point of interconnection is the Robert Bills-Wilmot 138kV Transmission Line.

The project is located in the western region of the United States. As of the latest data, no interconnection agreement (IA) status is available. Recent news coverage of the project may exist.

Generated from interconnection queue and public data sources

Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

AZ

County

Pima

Grid Region

Mountain West

Market

Developer

Utility

Tucson Electric Power Company

Entity

TEP

Service Type

NRIS

Point of Interconnection

Robert Bills-Wilmot 138kV Transmission Line

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
PALOVERDE
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.

No Ask reports yet for this entity.

Ask about Project TEP-132
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.