TEP-109
200 MW generation in Pima, AZ · In queue since December 2021 · Proposed COD May 2024
200 MW
Capacity
1
Components
Other
4y 11m
In Queue
—
IA Status
COD target: 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
2y 5m
Schedule
30 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-05-31
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of May 2024. No independent news or research sources to validate or update this date, which is now in the past.
Developer: TEP is Tucson Electric Power, a regulated utility. This appears to be a utility-owned project rather than a shell LLC structure, so no parent-subsidiary distinction needed.
Status: LBNL shows active queue status, but proposed COD is now 8+ months past. Without news or research sources, cannot determine if project proceeded to construction/operation or was delayed.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
TEP-109 is a proposed 200 MW generation project located in Pima County, Arizona. The project, developed by TEP (Tucson Electric Power Company), is listed in the CAISO interconnection queue as of December 21, 2021, with a proposed commercial operation date of May 31, 2024. The project's point of interconnection is the Vail 138kV Substation.
The project is categorized as "Other" technology, with 200 MW of capacity attributed to this technology type. The project is currently listed as active in the interconnection queue.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
AZ
County
Pima
Grid Region
Mountain West
Market
—
Developer
TEP
Utility
Tucson Electric Power Company
Entity
TEP
Service Type
NRIS
Point of Interconnection
Vail 138kV Substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.