Project TEP-108 — Project Summary

Queue ID
TEP-108
Capacity
200 MW
Technology
Other
Status
active
Location
Pima, AZ
Region
West
Developer
TEP
IA Status

TEP-108

TEP-108BetaActiveOtherTEPLBNL

200 MW generation in Pima, AZ · In queue since December 2021 · Proposed COD May 2024

BA: AZPSNERC: WECCRC: SPPW

200 MW

Capacity

1

Components

Other

4y 7m

In Queue

IA Status

COD target: 2024

Interconnection

Total Duration

2y 5m

Schedule

26 months past proposed COD

Pre-Study0%
Queue EntryDec 21, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-05-31

Cross-source intelligence
Beta
Medium confidence·1 sources·as of 2026-06-01
Expected COD
2024-05-31
From queue filing
Developer
Tucson Electric Power
Confirmed
Status
Active
Active — Arizona Corporation Commission approval obtained as of December 2024
Financing
Unannounced
Key milestones
Permit approvedDec 2024Most recent

Arizona Corporation Commission approved TEP project

source
About

TEP-108 is a proposed 200 MW generation project located in Pima County, Arizona. The project, developed by TEP (Tucson Electric Power Company), utilizes an unspecified "Other" technology. It is interconnected to the North Loop 138kV Substation.

The project is currently active in the West interconnection queue, with an entry date of December 21, 2021, and a proposed commercial operation date of May 31, 2024. The project has been mentioned in recent news coverage.

Generated from interconnection queue and public data sources

Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

AZ

County

Pima

Grid Region

Mountain West

Market

Developer

TEP

Utility

Tucson Electric Power Company

Entity

TEP

Service Type

NRIS

Point of Interconnection

North Loop 138kV Substation

Data Source

LBNL

ApplicantTucson Electric Power Co.The Arizona Republic · 2025-12-04
AgencyArizona Corporation CommissionThe Arizona Republic · 2025-12-04
RulingApprovalThe Arizona Republic · 2025-12-04
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
PALOVERDE
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (2)Beta

Last updated 2026-03-14