TEC-76
55 MW generation in Polk, FL · In queue since November 2020 · Proposed COD November 2023
55 MW
Capacity
1
Components
Solar
6 years
In Queue
IA Executed
IA Phase
COD target: 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3 years
Schedule
37 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2023-11-01
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
TEC-76 is a proposed 55 MW solar generation project located in Polk County, Florida, in the southeastern United States. The project consists of a single solar component with a capacity of 55 MW. No developer name is listed in the available interconnection data. The proposed point of interconnection is the Pebbledale Substation in Polk County, within the service territory of Tampa Electric Company (TEC).
The project entered Tampa Electric Company's interconnection queue on November 30, 2020, and remains in active status. It has requested Network Resource Interconnection Service (NRIS). Its interconnection agreement has been executed. The proposed commercial operation date was November 1, 2023. Tampa Electric administers its own queue rather than participating in an ISO/RTO, so the project is not part of an organized wholesale market queue.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
FL
County
Polk
Grid Region
Southeast
Market
—
Developer
—
Utility
Tampa Electric Company
Entity
TEC
Service Type
NRIS
Point of Interconnection
Pebbledale Substation, Polk County, Florida
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.