SRP-SRP-Q66
30 MW generation in Maricopa, AZ · In queue since November 2020 · Proposed COD October 2022
30 MW
Capacity
1
Components
Gas
5y 6m
In Queue
—
IA Status
COD target: 2022
Total Duration
1y 11m
Schedule
44 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-10-01
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
SRP-SRP-Q66 is a proposed 30 MW gas-fired generation project located in Maricopa County, Arizona. The project is listed in the Salt River Project (SRP) interconnection queue with a queue entry date of November 11, 2020. The proposed commercial operation date is October 1, 2022.
The project, which consists of 30 MW of gas-fired capacity, is currently listed as active in the interconnection queue. The point of interconnection is the Santan 69 kV substation.
Generated from interconnection queue and public data sources
State
AZ
County
Maricopa
Grid Region
Mountain West
Market
—
Developer
—
Utility
Salt River Project
Entity
SRP
Service Type
—
Point of Interconnection
Santan 69 kV
Data Source
LBNL
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project SRP-SRP-Q66Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.