Project SRP-Q2402 — Project Summary

Queue ID
SRP-Q2402
Capacity
300 MW
Technology
Solar+Battery
Status
active
Location
Maricopa, AZ
Region
West
Developer
IA Status

SRP-Q2402

SRP-Q2402BetaActiveSolarBatterySRPLBNL

300 MW hybrid in Maricopa, AZ · In queue since February 2024 · Proposed COD May 2027

300 MW

Capacity

2

Components

Solar + Battery

2y 3m

In Queue

IA Status

COD target: 2027

Interconnection

Total Duration

3y 3m

Study Phase

Cluster 24

Pre-Study0%
Queue EntryFeb 5, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-05-31

Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

AZ

County

Maricopa

Grid Region

Mountain West

Market

Developer

Utility

Salt River Project

Entity

SRP

Service Type

Point of Interconnection

Hassayampa 500 kV

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Technology
Solar150 MW · 50%
Battery150 MW · 50%
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
No news available for this project.

No Ask reports yet for this entity.

Ask about Project SRP-Q2402
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.