Project SPP-GI-TC-2024-30 — Project Summary

Queue ID
SPP-GI-TC-2024-30
Capacity
199.9 MW
Technology
Solar+Battery
Status
active
Location
Morgan County, CO
Region
SPP
Developer
—
IA Status
—

SPP-GI-TC-2024-30

SPP-GI-TC-2024-30BetaActiveHybrid / Solar/StorageSPPLive · SPP

199.9 MW generation in Morgan County, CO · In queue since May 2024 · Proposed COD March 2028

BA: PSCOISO/RTO: SPPNERC: WECCRC: SPPW

199.9 MW

Capacity

0

Components

2y 5m

In Queue

—

IA Status

COD target: 2028

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

4 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

3y 10m

Pre-Study0%
Queue EntryMay 29, 2024

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-03-01

About

Queue ID SPP-GI-TC-2024-30 is a proposed solar and battery storage hybrid development project in Morgan County, Colorado. The project has a total capacity of 199.9 MW and is classified as a generation project. The data does not give separate capacities for the solar and storage components. No developer is identified. The project would interconnect at the Story 230 Substation, in the transmission system of Tri-State Generation and Transmission Association (TSGT).

The project is in the interconnection queue of the Southwest Power Pool (SPP), which it entered on May 29, 2024. It currently holds active status. It has requested both Energy Resource (ER) and Network Resource (NR) interconnection service. The proposed commercial operation date is March 1, 2028. The available data does not report the status of an interconnection agreement.

Generated from interconnection queue and public data sources

Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

CO

County

Morgan County

Grid Region

SPP (Southwest Power Pool)

Market

ISO/RTO Member

Developer

—

Utility

TSGT

Entity

SPP

Service Type

ER/NR

Point of Interconnection

Story 230 Substation

Data Source

Live · SPP

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
SPP
Trading Hub
SPP North Hub
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.

No Ask reports yet for this entity.

Ask about Project SPP-GI-TC-2024-30
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.