TSGT-GI-SISS-2025-05
150 MW storage in Kit Carson, CO · In queue since August 2025 · Proposed COD September 2027
150 MW
Capacity
1
Components
Battery
1y 3m
In Queue
In Progress (unknown study)
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
2y 1m
Study Phase
Surplus Interconnection Service - 2025
Interconnection request submitted to ISO/RTO
IA FULLY EXECUTED/ON SCHEDULE
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-30
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
TSGT-GI-SISS-2025-05 is a proposed 150 MW battery energy storage development project located in Kit Carson County, Colorado, in the western United States. The project is listed in the interconnection queue of Tri-State Generation and Transmission Association (TSGT), which serves as the transmission provider. The proposed point of interconnection is the Burlington 230kV Substation. No developer or project name has been publicly identified in the queue data, so the project is referenced by its queue identifier.
The project entered the TSGT queue on August 8, 2025, and holds an active status. It requested Network Resource Interconnection Service (NRIS) and is being evaluated as part of the 2025 Surplus Interconnection Service study phase. Its interconnection agreement status is listed as in progress, though the specific study stage is not identified. The project has a proposed commercial operation date of September 30, 2027.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- SPP queue source as of: Oct 22, 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CO
County
Kit Carson
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Service Type
NRIS
Point of Interconnection
Burlington 230kV Substation
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.