TSGT-GI-CS-2025-29
300 MW hybrid in Yuma, CO · In queue since October 2025 · Proposed COD August 2031
300 MW
Capacity
1
Components
Solar
1y 1m
In Queue
Cluster Study
IA Phase
COD target: 2031
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 10m
Study Phase
GI 2025 Cluster Study
Interconnection request submitted to ISO/RTO
FACILITY STUDY STAGE
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-08-01
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
TSGT-GI-CS-2025-29 is a proposed hybrid energy development project in Yuma County, Colorado, in the western United States. The project is classified as a Solar+Battery facility with a total capacity of 300 MW. Its technology listing also includes solar, wind, and battery storage, but the component breakdown specifies only a 300 MW solar portion and gives no separate capacities for the wind or battery elements. The developer has not been publicly identified in the queue data.
The project entered the interconnection queue of Tri-State Generation and Transmission Association (TSGT) on October 6, 2025, and its status is active. It is being evaluated in Tri-State's GI 2025 Cluster Study, and its interconnection agreement status is listed as "Cluster Study." The proposed point of interconnection is the Burlington–Wray 230 kV transmission line. The project has requested Energy Resource Interconnection Service (ERIS), and its proposed commercial operation date is August 1, 2031.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- SPP queue source as of: Oct 22, 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CO
County
Yuma
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Service Type
ERIS
Point of Interconnection
Burlington - Wray 230kV Line
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.