Project SPP-GEN-2026-SR30 — Project Summary

Queue ID
SPP-GEN-2026-SR30
Capacity
504 MW
Technology
Battery
Status
active
Location
Hodgeman and Ford, KS
Region
SPP
Developer
—
IA Status
—

SPP-GEN-2026-SR30

SPP-GEN-2026-SR30BetaActiveBattery/StorageSPPLive · SPP

504 MW storage in Hodgeman and Ford, KS · In queue since June 2026 · Proposed COD September 2030

BA: SWPPISO/RTO: SPPNERC: SPPRC: SPP

504 MW

Capacity

0

Components

4 months

In Queue

—

IA Status

COD target: 2030

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

4 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

4y 3m

Pre-Study0%
Queue EntryJun 4, 2026

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-09-13

About

SPP-GEN-2026-SR30 is a proposed battery energy storage development project located in Hodgeman and Ford counties, Kansas. The project has a total capacity of 504 MW and is classified as a standalone storage facility using battery technology. No developer or project name has been publicly identified in the queue data. The project is proposed to interconnect at the Spearville–Holcomb 345 kV transmission line, which is owned by Sunflower Electric Power Corporation (SUNC).

The project is listed in the Southwest Power Pool (SPP) interconnection queue, which it entered on June 4, 2026. It has requested Energy Resource (ER) interconnection service, and its status in the queue is active. The proposed commercial operation date is September 13, 2030. The available data does not indicate whether an interconnection agreement has been executed.

Generated from interconnection queue and public data sources

Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

KS

County

Hodgeman and Ford

Grid Region

SPP (Southwest Power Pool)

Market

ISO/RTO Member

Developer

—

Utility

SUNC

Entity

SPP

Service Type

ER

Point of Interconnection

SUNC Spearville - Holcomb 345kV

Data Source

Live · SPP

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
SPP
Trading Hub
SPP North Hub
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.

No Ask reports yet for this entity.

Ask about Project SPP-GEN-2026-SR30
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.