SPP-GEN-2026-PR5
60.4 MW storage in Goultry, OK · In queue since January 2026
60.4 MW
Capacity
0
Components
4 months
In Queue
—
IA Status
Total Duration
4 months
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
SPP-GEN-2026-PR5 is a proposed 60.4 MW battery storage project located in Goultry County, Oklahoma. The project is in the Southwest Power Pool (SPP) interconnection queue, having entered the queue on January 7, 2026. OG&E is the utility associated with the project. The point of interconnection is the Woodring 345kV Substation.
The project's service type is listed as Energy Resource (ER). As of the latest data, the project remains in active status within the SPP queue.
Generated from interconnection queue and public data sources
State
OK
County
Goultry
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
OG&E
Entity
SPP
Service Type
ER
Point of Interconnection
Woodring 345kV Substation
Data Source
Live · SPP
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- OKGE.WFEC.SKLCRKSLR
- POI Substation
- Woodring Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.