SPP-GEN-2026-PR22
104.4 MW storage in Rogers, NM · In queue since June 2026 · Proposed COD May 2028
104.4 MW
Capacity
0
Components
4 months
In Queue
—
IA Status
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
1y 11m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-03
SPP-GEN-2026-PR22 is a proposed battery energy storage development project with a total capacity of 104.4 MW. According to queue records, the project is located in Rogers County, New Mexico, within the Southwest Power Pool (SPP) region. The developer has not been publicly identified in the available data. The project would interconnect at the Sagamore Wind South 345 kV point of interconnection in the service territory of Southwestern Public Service Company (SPS).
The project entered the SPP interconnection queue on June 18, 2026, and currently holds an active status. It has requested Network Resource (NR) interconnection service and has a proposed commercial operation date of May 3, 2028. The status of an interconnection agreement is not indicated in the available queue data.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NM
County
Rogers
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SPS
Entity
SPP
Service Type
NR
Point of Interconnection
Sagamore Wind South 345kV
Data Source
Live · SPP
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project SPP-GEN-2026-PR22Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.