SPP-GEN-2025-SR4
150 MW storage in Edwards, KS · In queue since August 2025 · Proposed COD December 2028
150 MW
Capacity
1
Components
Battery
11 months
In Queue
Facility Study
IA Phase
COD target: 2028
Total Duration
3y 4m
Study Phase
Surplus; 03 CENTRAL
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
SPP-GEN-2025-SR4 is a proposed 150 MW battery storage project located in Kinsley, Kansas. The project is listed in the Southwest Power Pool (SPP) interconnection queue with an entry date of August 18, 2025. The proposed project's point of interconnection (POI) is the Great Bend-Spearville 230kV line.
The project, which has an active status in the queue, is being developed within the Sunflower Electric Power Corporation (SUNC) service area. It is designated as providing both Energy Resource (ER) and Network Resource (NR) service.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
KS
County
Edwards
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SUNC
Entity
SPP
Service Type
NRIS/ERIS
Point of Interconnection
Great Bend-Spearville 230kV line
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.