SPP-GEN-2024-SR12
20 MW storage in Lamoure, ND · In queue since May 2024 · Proposed COD October 2026
20 MW
Capacity
1
Components
Battery
2y 2m
In Queue
IA Pending
IA Phase
COD target: 2026
Total Duration
2y 5m
Study Phase
Surplus; 01 NORTH
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-10-01
SPP-GEN-2024-SR12 is a proposed 20 MW battery storage project located in Lamoure County, North Dakota. The project, which consists of a single 20 MW battery component, is in the Southwest Power Pool (SPP) interconnection queue under queue ID SPP-GEN-2024-SR12. The queue entry date is May 21, 2024, and the proposed commercial operation date is October 1, 2026. The interconnecting utility is Western Area Power Administration (WAPA).
As of the latest data, the project's interconnection agreement (IA) status is listed as "IA Pending". The point of interconnection (POI) is the Edgeley 115 kV Substation. There has been recent news coverage of the project.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
ND
County
Lamoure
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
WAPA
Entity
SPP
Service Type
ERIS
Point of Interconnection
Edgeley 115 kV Substation
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- POI Substation
- Edgeley Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.