SPP-GEN-2024-327
200 MW storage in Ward, ND · In queue since March 2025 · Proposed COD January 2028
200 MW
Capacity
1
Components
Battery
1y 4m
In Queue
System Impact Study
IA Phase
COD target: 2028
Total Duration
2y 10m
Study Phase
DISIS-2024-001; 01 NORTH
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-01-01
SPP-GEN-2024-327 is a proposed 200 MW battery storage project located in Ward County, North Dakota. The project is listed in the Southwest Power Pool (SPP) interconnection queue under queue ID SPP-GEN-2024-327, with a queue entry date of March 1, 2025. The designated point of interconnection (POI) is the Berthold 115 kV Substation. The project's listed service type is ER/NR.
The developer is not specified in the data, but the utility is listed as CPEC. The project is currently listed as active in the SPP queue. A proposed commercial operation date and interconnection agreement (IA) status are not available in the provided data. Recent news coverage of the project is not indicated.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
ND
County
Ward
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
CPEC
Entity
SPP
Service Type
NRIS/ERIS
Point of Interconnection
Berthold 115 kV Substation
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- WAUE_NSP_BERTHOLD
- POI Substation
- Berthold Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.