SPP-GEN-2024-082
745 MW generation in Williams, ND · In queue since October 2024 · Proposed COD March 2030
745 MW
Capacity
1
Components
Gas
1y 7m
In Queue
System Impact Study
IA Status
COD target: 2030
Total Duration
5y 5m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-03-01
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
SPP-GEN-2024-082 is a proposed 745 MW gas-fired generation project located in Williams County, North Dakota. The project is listed in the Southwest Power Pool (SPP) interconnection queue, with an entry date of October 30, 2024. The proposed commercial operation date is March 1, 2030. The Balancing Authority is BEPC.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection (POI) is the Springbrook - Tande 345 kV Line.
Generated from interconnection queue and public data sources
State
ND
County
Williams
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
BEPC
Entity
SPP
Service Type
—
Point of Interconnection
Springbrook - Tande 345 kV Line
Data Source
LBNL + Live
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project SPP-GEN-2024-082Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.