217 MW generation in Lancaster, NE · In queue since October 2023 · Proposed COD June 2029
217 MW
Capacity
1
Components
Gas
2y 9m
In Queue
Facility Study
IA Phase
COD target: 2029
Total Duration
5y 8m
Study Phase
DISIS-2023-001; 02 NEBRASKA
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-06-01
SPP-GEN-2023-225 is a proposed 217 MW gas-fired generation project located in Lancaster County, Nebraska. The project is listed in the Southwest Power Pool (SPP) interconnection queue under queue ID SPP-GEN-2023-225, with an entry date of October 2, 2023. The proposed commercial operation date is June 1, 2027. Nebraska Public Power District (NPPD) is the interconnecting utility.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection (POI) is the Olive Creek 345 kV Substation.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NE
County
Lancaster
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
NPPD
Entity
SPP
Service Type
ERIS
Point of Interconnection
Olive Creek 345 kV Substation
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project SPP-GEN-2023-225Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.