SPP-GEN-2023-135
52 MW generation in Bowie, TX · In queue since October 2023 · Proposed COD December 2026
52 MW
Capacity
1
Components
Solar
2y 9m
In Queue
Facility Study
IA Phase
COD target: 2026
Total Duration
3y 2m
Study Phase
DISIS-2023-001; 04 SOUTHEAST
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
SPP-GEN-2023-135 is a proposed 52 MW solar generation project located in Bowie County, Texas. The project is in the Southwest Power Pool (SPP) interconnection queue, with an entry date of October 2, 2023. The proposed commercial operation date is December 31, 2026. The interconnection request is currently in the System Impact Study phase. The point of interconnection is the Lydia 345kV substation, and the interconnecting utility is AEP.
The development project consists of 52 MW of solar photovoltaic generation. It is currently listed as an active project within the SPP queue.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Bowie
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
SPP
Service Type
NRIS/ERIS
Point of Interconnection
Lydia 345kV substation
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project SPP-GEN-2023-135Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.