SPP-GEN-2023-033
200 MW storage in Clay, MO · In queue since October 2023 · Proposed COD July 2028
200 MW
Capacity
1
Components
Battery
2y 9m
In Queue
Facility Study
IA Phase
COD target: 2028
Total Duration
4y 9m
Study Phase
DISIS-2023-001; 03 CENTRAL
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-01
SPP-GEN-2023-033 is a proposed 200 MW battery storage project located in Clay County, Missouri. The project is in the Southwest Power Pool (SPP) interconnection queue, with an entry date of October 2, 2023, and a proposed commercial operation date of July 1, 2028. The project's interconnection point is the Liberty South 161 kV Substation, and the interconnecting utility is Evergy.
The project is currently in the System Impact Study phase of the interconnection process. The developer is unknown. The project has appeared in recent news coverage regarding Evergy's grid modernization plans.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MO
County
Clay
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
WERE
Entity
SPP
Service Type
NRIS/ERIS
Point of Interconnection
Liberty South 161 kV Substation
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- KCPL.VOLT.0263
- POI Substation
- Liberty South
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.