SPP-GEN-2022-214
239 MW generation in Sumner, KS · In queue since March 2023 · Proposed COD June 2030
239 MW
Capacity
1
Components
Solar
3y 7m
In Queue
Facility Study
IA Phase
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
7y 3m
Study Phase
DISIS-2022-001; 03 CENTRAL
Interconnection request submitted to ISO/RTO
IA FULLY EXECUTED/ON SCHEDULE
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-06-15
SPP-GEN-2022-214 is a proposed 239 MW solar generation project located in Sumner County, Kansas. The development project consists of a single solar component with a capacity of 239 MW. No developer is identified in the available queue data. The project is planned to interconnect at the Gill–Viola 138 kV Line Break, within the service territory of the transmitting utility identified as WERE (Evergy Kansas Central, formerly Westar Energy).
The project entered the Southwest Power Pool (SPP) interconnection queue on March 2, 2023, and holds an active status. It is being evaluated under the DISIS-2022-001 definitive interconnection system impact study cluster, within the 03 Central study group. The project has requested Energy Resource Interconnection Service (ERIS). Its interconnection agreement process is at the Facility Study stage, and it has a proposed commercial operation date of June 15, 2030.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
KS
County
Sumner
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
WERE
Entity
SPP
Service Type
ERIS
Point of Interconnection
Gill - Viola 138 kV Line Break
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project SPP-GEN-2022-214Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.