SPP-GEN-2022-156
100 MW storage in Creek, OK · In queue since February 2023 · Proposed COD June 2029
100 MW
Capacity
1
Components
Battery
3y 8m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
6y 4m
Study Phase
DISIS-2022-001; 04 SOUTHEAST
Interconnection request submitted to ISO/RTO
IA FULLY EXECUTED/ON SCHEDULE
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-06-01
SPP-GEN-2022-156 is a proposed 100 MW battery energy storage project in Creek County, Oklahoma. It consists of a single battery component rated at 100 MW and is classified as a storage project. The proposed point of interconnection is the Silver City 138 kV Substation, within the service territory of the Grand River Dam Authority (GRDA). No developer has been publicly identified in the queue data.
The project is listed as active in the Southwest Power Pool (SPP) generation interconnection queue, which it entered on February 24, 2023. It has requested Energy Resource Interconnection Service (ERIS) and is being evaluated in the DISIS-2022-001 study cluster within the 04 Southeast study area. Its interconnection agreement status is Facility Study, and its proposed commercial operation date is June 1, 2029.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OK
County
Creek
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
GRDA
Entity
SPP
Service Type
ERIS
Point of Interconnection
Silver City 138 kV Substation
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- POI Substation
- Silver City
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project SPP-GEN-2022-156Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.