SPP-GEN-2021-103
150 MW storage in Johnson, KS · In queue since May 2021 · Proposed COD March 2030
150 MW
Capacity
1
Components
Battery
5y 5m
In Queue
IA Executed
IA Phase
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
8y 10m
Study Phase
DISIS-2021-001; 03 CENTRAL
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
IA FULLY EXECUTED/ON SCHEDULE
Project under construction
Typical: 6–18 months
Proposed COD: 2030-03-31
SPP-GEN-2021-103 is a proposed 150 MW battery energy storage development project located in Johnson County, Kansas. The standalone storage project consists of a single battery component rated at 150 MW. It is planned to interconnect at Evergy's Atlantic Substation 115 kV bus, within the service territory of the transmitting utility identified as WERE. No developer or project name has been publicly identified in the available queue data.
The project is listed in the Southwest Power Pool (SPP) interconnection queue, which it entered on May 25, 2021, and currently holds active status. It requested both Network Resource Interconnection Service (NRIS) and Energy Resource Interconnection Service (ERIS). The project was studied as part of the DISIS-2021-001 cluster within the 03 Central study group. An interconnection agreement (IA) has been executed for the project, and its proposed commercial operation date is March 31, 2030.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
KS
County
Johnson
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
WERE
Entity
SPP
Service Type
NRIS/ERIS
Point of Interconnection
Evergy's Atlantic Substation115kV bus
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- POI Substation
- Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project SPP-GEN-2021-103Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.