SPP-GEN-2021-048
75 MW storage in Lancaster, NE · In queue since April 2021 · Proposed COD September 2029
75 MW
Capacity
1
Components
Battery
5y 6m
In Queue
IA Executed
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
8y 5m
Study Phase
DISIS-2021-001; 02 NEBRASKA
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
IA FULLY EXECUTED/ON SCHEDULE
Project under construction
Typical: 6–18 months
Proposed COD: 2029-09-01
SPP-GEN-2021-048 is a proposed 75 MW battery energy storage development project located in Lancaster County, Nebraska. The project consists of a single battery storage component rated at 75 MW. It would interconnect at the Wagener 115kV Substation within the service territory of Lincoln Electric System (LES). No developer has been publicly identified in the queue data.
The project is listed as active in the Southwest Power Pool (SPP) interconnection queue, which it entered on April 30, 2021. It was evaluated as part of the DISIS-2021-001 definitive interconnection system impact study cluster, in the 02 Nebraska study group. The project has requested both Network Resource Interconnection Service (NRIS) and Energy Resource Interconnection Service (ERIS). An interconnection agreement has been executed. The proposed commercial operation date is September 1, 2029.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NE
County
Lancaster
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
LES
Entity
SPP
Service Type
NRIS/ERIS
Point of Interconnection
Wagener 115kV Substation
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- POI Substation
- Wagener Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project SPP-GEN-2021-048Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.