Project SPP-GEN-2021-027 — Project Summary

Queue ID
SPP-GEN-2021-027
Capacity
102.06 MW
Technology
Solar
Status
suspended
Location
Lancaster, NE
Region
SPP
Developer
—
IA Status
Facility Study

SPP-GEN-2021-027

SPP-GEN-2021-027BetaSuspendedSolarSPPLBNL + Live

102.06 MW generation in Lancaster, NE · In queue since May 2021 · Proposed COD June 2029

BA: SWPPISO/RTO: SPPNERC: MRORC: SPP

102.06 MW

Capacity

1

Components

Solar

5y 5m

In Queue

Facility Study

IA Phase

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

4 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

8y 1m

Study Phase

DISIS-2021-001; 02 NEBRASKA

Suspended50%
Queue EntryMay 14, 2021

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-06-01

About

SPP-GEN-2021-027 is a proposed solar generation project located in Lancaster County, Nebraska, within the Southwest Power Pool (SPP) region. The development project has a total capacity of 102.06 MW, consisting entirely of solar generation. It is proposed to interconnect at the Olive Creek 115 kV Substation, with Nebraska Public Power District (NPPD) as the associated utility. The project has requested Energy Resource Interconnection Service (ERIS).

The project entered the SPP interconnection queue on May 14, 2021, and was studied in the DISIS-2021-001 cluster within the 02 Nebraska study group. Its interconnection agreement status is listed as Facility Study. The project's queue status is currently suspended. It has a proposed commercial operation date of June 1, 2029.

Generated from interconnection queue and public data sources

Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

NE

County

Lancaster

Grid Region

SPP (Southwest Power Pool)

Market

ISO/RTO Member

Developer

—

Utility

NPPD

Entity

SPP

Service Type

ERIS

Point of Interconnection

Olive Creek 115 kV Substation

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
SPP
Trading Hub
SPP North Hub
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.

No Ask reports yet for this entity.

Ask about Project SPP-GEN-2021-027
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.