SPP-GEN-2021-021
150 MW generation in Stevens, KS · In queue since April 2021 · Proposed COD December 2029
150 MW
Capacity
1
Components
Wind
5y 6m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
8y 8m
Study Phase
DISIS-2021-001; 03 CENTRAL
Interconnection request submitted to ISO/RTO
IA FULLY EXECUTED/ON SCHEDULE
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-31
SPP-GEN-2021-021 is a proposed 150 MW wind generation project located in Stevens County, Kansas. The development project is listed in the interconnection queue of the Southwest Power Pool (SPP), with Southwestern Public Service (SPS) identified as the associated utility. The project's developer has not been publicly identified in the queue data. It proposes to interconnect at the Carpenter 345 kV Substation and has requested Energy Resource Interconnection Service (ERIS).
The project entered the SPP queue on April 20, 2021, and remains in active status. It is being evaluated as part of the DISIS-2021-001 cluster study (03 CENTRAL), and its interconnection agreement status is listed as "Facility Study." The proposed commercial operation date is December 31, 2029.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
KS
County
Stevens
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SPS
Entity
SPP
Service Type
ERIS
Point of Interconnection
Carpenter 345 kV Substation
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project SPP-GEN-2021-021Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.