SPP-GEN-2020-065
1,003 MW generation in Gaines, NM · In queue since April 2020 · Proposed COD July 2028
1,003 MW
Capacity
1
Components
Gas
6y 6m
In Queue
IA Executed
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
8y 3m
Study Phase
DISIS-2020-001; 05 SOUTHWEST
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
IA FULLY EXECUTED/ON SCHEDULE
Project under construction
Typical: 24–48 months
Proposed COD: 2028-07-02
SPP-GEN-2020-065 is a proposed natural gas-fired generation project with a total capacity of 1,003 MW. The queue record lists its location as Gaines County, New Mexico, within the Southwest Power Pool (SPP) region, and the transmission owner is Southwestern Public Service (SPS). The project would connect to the grid at the Hobbs-Andrews 345 kV Line. No developer is identified in the available queue data.
The project entered the SPP interconnection queue on April 30, 2020, and remains active. It was studied in the DISIS-2020-001 cluster, within the 05 Southwest study area, and requested Energy Resource Interconnection Service (ERIS). An interconnection agreement has been executed. The proposed commercial operation date is July 2, 2028.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NM
County
Gaines
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SPS
Entity
SPP
Service Type
ERIS
Point of Interconnection
Hobbs-Andrews 345 kV Line
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project SPP-GEN-2020-065Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.