SPP-GEN-2020-060
200 MW storage in Lubbock, TX · In queue since April 2020 · Proposed COD June 2031
200 MW
Capacity
1
Components
Battery
6y 6m
In Queue
IA Pending
IA Phase
COD target: 2031
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
11y 2m
Study Phase
DISIS-2020-001; 05 SOUTHWEST
Interconnection request submitted to ISO/RTO
IA FULLY EXECUTED/ON SCHEDULE
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-06-01
SPP-GEN-2020-060 is a proposed 200 MW battery energy storage development project located in Lubbock County, Texas. The project consists of a single battery storage component with a capacity of 200 MW. It is planned to interconnect at the Lubbock East Substation 230 kV within the service territory of Southwestern Public Service (SPS). No developer or project name has been disclosed in the available queue data.
The project is in the Southwest Power Pool (SPP) interconnection queue, which it entered on April 30, 2020, and it remains in active status. It is being studied as part of the DISIS-2020-001 definitive interconnection system impact study cluster, in the 05 Southwest study group. The project has requested Energy Resource Interconnection Service (ERIS). Its interconnection agreement is listed as pending. The proposed commercial operation date is June 1, 2031, more than eleven years after the project first entered the queue.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Lubbock
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SPS
Entity
SPP
Service Type
ERIS
Point of Interconnection
Lubbock East Substation 230 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- POI Substation
- Lubbock East Interchange
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project SPP-GEN-2020-060Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.