SPP-GEN-2019-053
50 MW storage in Edwards, KS · In queue since May 2019 · Proposed COD December 2028
50 MW
Capacity
1
Components
Battery
7y 5m
In Queue
IA Executed
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
9y 7m
Study Phase
DISIS-2019-001; 03 CENTRAL
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
IA FULLY EXECUTED/ON SCHEDULE
Project under construction
Typical: 6–18 months
Proposed COD: 2028-12-01
SPP-GEN-2019-053 is a proposed 50 MW battery energy storage development project located in Edwards County, Kansas. The project consists of a single battery storage component with a capacity of 50 MW. It would connect to the transmission system at the Great Bend-Spearville 230 kV line, within the service territory of Sunflower Electric Power Corporation (SUNC). No developer has been publicly identified in the available queue data.
The project is in the interconnection queue of the Southwest Power Pool (SPP), which it entered on May 24, 2019. It was evaluated in the DISIS-2019-001 cluster study, in the 03 Central study area, and has requested both Network Resource Interconnection Service (NRIS) and Energy Resource Interconnection Service (ERIS). The project's queue status is listed as active, and an interconnection agreement has been executed. The proposed commercial operation date is December 1, 2028.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
KS
County
Edwards
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SUNC
Entity
SPP
Service Type
NRIS/ERIS
Point of Interconnection
Great Bend-Spearville 230kV line
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project SPP-GEN-2019-053Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.