SPP-GEN-2019-044
100 MW generation in Ford, KS · In queue since May 2019 · Proposed COD June 2030
100 MW
Capacity
1
Components
Solar
7y 5m
In Queue
IA Executed
IA Phase
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
11y 1m
Study Phase
DISIS-2019-001; 03 CENTRAL
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
IA FULLY EXECUTED/ON SCHEDULE
Project under construction
Typical: 12–24 months
Proposed COD: 2030-06-15
SPP-GEN-2019-044 is a proposed 100 MW solar generation project located in Ford County, Kansas. The development project consists of a single solar component with a capacity of 100 MW. No developer is identified in the available queue data. The project is planned to interconnect at the North Fort Dodge 115kV Substation, within the service territory of Sunflower Electric Power Corporation (SUNC).
The project entered the Southwest Power Pool (SPP) interconnection queue on May 24, 2019, and remains in active status. It was studied as part of the DISIS-2019-001 cluster in the 03 CENTRAL study group. The project has requested Energy Resource Interconnection Service (ERIS) and has an executed interconnection agreement (IA). Its proposed commercial operation date is June 15, 2030.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
KS
County
Ford
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SUNC
Entity
SPP
Service Type
ERIS
Point of Interconnection
North Fort Dodge 115kV Substation
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project SPP-GEN-2019-044Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.