SPP-GEN-2019-011
207 MW storage in Yoakum, TX · In queue since April 2019 · Proposed COD June 2028
207 MW
Capacity
1
Components
Battery
7y 6m
In Queue
IA Executed
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
9y 2m
Study Phase
DISIS-2019-001; 05 SOUTHWEST
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
IA FULLY EXECUTED/ON SCHEDULE
Project under construction
Typical: 6–18 months
Proposed COD: 2028-06-01
SPP-GEN-2019-011 is a proposed battery energy storage development project located in Yoakum County, Texas, within the Southwest Power Pool (SPP) region. The project has a total proposed capacity of 207 MW, consisting entirely of a single battery storage component. No developer is identified in the available queue data. The project is planned to interconnect at the Yoakum 345kV Substation, with Southwestern Public Service (SPS) as the associated transmission utility.
The project entered the SPP interconnection queue on April 22, 2019, and currently holds an active status. It was evaluated as part of the DISIS-2019-001 study cycle in the 05 Southwest study area. It has requested both Network Resource Interconnection Service (NRIS) and Energy Resource Interconnection Service (ERIS). An interconnection agreement has been executed for the project, marking an advanced stage in the interconnection process. The proposed commercial operation date is June 1, 2028.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Yoakum
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SPS
Entity
SPP
Service Type
NRIS/ERIS
Point of Interconnection
Yoakum 345kV Substation
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- POI Substation
- Yoakum Gaetner Road Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project SPP-GEN-2019-011Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.