SPP-GEN-2018-067
255 MW generation in Williams, ND · In queue since October 2018 · Proposed COD May 2028
255 MW
Capacity
1
Components
Wind
8 years
In Queue
IA Executed
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
9y 7m
Study Phase
DISIS-2018-002; 01 NORTH
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
IA FULLY EXECUTED/ON SCHEDULE
Project under construction
Typical: 18–36 months
Proposed COD: 2028-05-31
SPP-GEN-2018-067 is a proposed 255 MW wind generation project located in Williams County, North Dakota. The development project is listed in the interconnection queue of the Southwest Power Pool (SPP), with Mountrail-Williams Electric Cooperative (MWEC) identified as the interconnecting utility. No developer or project name is identified in the queue data. The project would connect to the grid at the 115 kV Strandahl substation and has requested Energy Resource Interconnection Service (ERIS).
The project entered the SPP queue on October 25, 2018, and remains in active status. It was evaluated as part of SPP's Definitive Interconnection System Impact Study cluster DISIS-2018-002, within the 01 North study group. An interconnection agreement (IA) has been executed for the project, a significant milestone in the interconnection process. The proposed commercial operation date is May 31, 2028, nearly ten years after its initial queue entry.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
ND
County
Williams
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
MWEC
Entity
SPP
Service Type
ERIS
Point of Interconnection
115kV Strandahl sub
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project SPP-GEN-2018-067Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.