SPP-GEN-2018-052
70 MW storage in Lea, NM · In queue since May 2018 · Proposed COD December 2027
70 MW
Capacity
1
Components
Battery
8y 5m
In Queue
IA Executed
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
9y 7m
Study Phase
DISIS-2018-001; 05 SOUTHWEST
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
IA FULLY EXECUTED/ON SCHEDULE
Project under construction
Typical: 6–18 months
Proposed COD: 2027-12-31
SPP-GEN-2018-052 is a proposed 70 MW battery energy storage development project located in Lea County, New Mexico. The project consists of a single battery component and is in the interconnection queue of the Southwest Power Pool (SPP), with Southwestern Public Service (SPS) as the interconnecting utility. No developer has been publicly identified in the queue data. The project would connect to the grid at the Roadrunner 115kV Substation and has requested Energy Resource Interconnection Service (ERIS).
The project entered the SPP interconnection queue on May 29, 2018, and was studied as part of the DISIS-2018-001 cluster in the 05 Southwest study area. It remains in active status, and an interconnection agreement has been executed. The proposed commercial operation date is December 31, 2027.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NM
County
Lea
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SPS
Entity
SPP
Service Type
ERIS
Point of Interconnection
Roadrunner 115kV Substation
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- POI Substation
- Roadrunner Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project SPP-GEN-2018-052Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.