SPP-GEN-2017-234
115 MW generation in Greeley, NE · In queue since November 2017 · Proposed COD July 2028
115 MW
Capacity
1
Components
Wind
8y 11m
In Queue
IA Executed
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
10y 8m
Study Phase
DISIS-2017-002; 02 NEBRASKA
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 18–36 months
Proposed COD: 2028-07-01
SPP-GEN-2017-234 is a proposed 115 MW wind generation project located in Greeley County, Nebraska. The development project is listed in the Southwest Power Pool (SPP) interconnection queue, with Nebraska Public Power District (NPPD) as the associated transmission utility. No developer is identified in the available queue data. The project's proposed point of interconnection is the Spalding to North Loup 115 kV transmission line. It has requested Energy Resource Interconnection Service (ERIS).
The project entered the SPP queue on November 6, 2017, and was studied as part of the DISIS-2017-002 cluster in the 02 Nebraska study group. An interconnection agreement (IA) has been executed for the project. However, its current queue status is listed as suspended. The proposed commercial operation date is July 1, 2028.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NE
County
Greeley
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
NPPD
Entity
SPP
Service Type
ERIS
Point of Interconnection
Spalding to North Loup 115kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project SPP-GEN-2017-234Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.