Project SPP-GEN-2017-215 — Project Summary

Queue ID
SPP-GEN-2017-215
Capacity
100 MW
Technology
Wind
Status
active
Location
Ward, ND
Region
SPP
Developer
—
IA Status
IA Executed

SPP-GEN-2017-215

SPP-GEN-2017-215BetaActiveWindSPPLBNL + Live

100 MW generation in Ward, ND · In queue since November 2017 · Proposed COD December 2030

BA: MISOISO/RTO: SPPNERC: MRORC: SPP

100 MW

Capacity

1

Components

Wind

8y 11m

In Queue

IA Executed

IA Phase

COD target: 2030

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

4 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

13y 1m

Study Phase

DISIS-2017-002; 01 NORTH

Construction75%
Queue EntryNov 30, 2017

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

IA FULLY EXECUTED/ON SCHEDULE

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2030-12-31

About

SPP-GEN-2017-215 is a proposed 100 MW wind generation project located in Ward County, North Dakota. The development project is listed in the interconnection queue of the Southwest Power Pool (SPP), with Basin Electric Power Cooperative (BEPC) identified as the associated utility. No developer name is specified in the queue data. The project consists of a single wind component totaling 100 MW and is proposed to connect to the grid at the Logan 230kV Substation.

The project entered the SPP queue on November 30, 2017, and currently holds an active status. It was evaluated as part of the DISIS-2017-002 Definitive Interconnection System Impact Study cluster, within the 01 North study group. The project has requested both Network Resource Interconnection Service (NRIS) and Energy Resource Interconnection Service (ERIS). An interconnection agreement has been executed, and the proposed commercial operation date is December 31, 2030.

Generated from interconnection queue and public data sources

Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

ND

County

Ward

Grid Region

SPP (Southwest Power Pool)

Market

ISO/RTO Member

Developer

—

Utility

BEPC

Entity

SPP

Service Type

NRIS/ERIS

Point of Interconnection

Logan 230kV Substation

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
SPP
Trading Hub
SPP North Hub
Hub Confidence
HIGH
POI Substation
Logan Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.

No Ask reports yet for this entity.

Ask about Project SPP-GEN-2017-215
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.