SPP-GEN-2017-195
500.4 MW generation in Johnson, KS · In queue since November 2017 · Proposed COD December 2030
500.4 MW
Capacity
1
Components
Solar
8y 11m
In Queue
IA Executed
IA Phase
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
13y 1m
Study Phase
DISIS-2017-002; 03 CENTRAL
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
IA FULLY EXECUTED/ON SCHEDULE
Project under construction
Typical: 12–24 months
Proposed COD: 2030-12-01
SPP-GEN-2017-195 is a proposed 500.4 MW solar generation project located in Johnson County, Kansas. The development project is listed in the interconnection queue of the Southwest Power Pool (SPP), with KCPL as the associated transmission utility. It is planned to connect to the grid at the West Gardner 345kV point of interconnection and has requested both Network Resource Interconnection Service and Energy Resource Interconnection Service (NRIS/ERIS). No developer is identified in the available queue data.
The project entered the SPP queue on November 30, 2017, and was studied as part of the DISIS-2017-002 cluster in the 03 Central study area. Its interconnection request remains active, and an interconnection agreement (IA) has been executed. The proposed commercial operation date is December 1, 2030, more than thirteen years after the project's initial queue entry.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
KS
County
Johnson
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
KCPL
Entity
SPP
Service Type
NRIS/ERIS
Point of Interconnection
West Gardner 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- KCPLBULLCRK5UNWGR1
- POI Substation
- West Gardner Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project SPP-GEN-2017-195Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.