SPP-GEN-2016-147
40 MW generation in Cheyenne, NE · In queue since November 2016 · Proposed COD June 2024
40 MW
Capacity
1
Components
Solar
9y 11m
In Queue
IA Executed
IA Phase
COD target: 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
7y 7m
Schedule
28 months past proposed COD
Study Phase
DISIS-2016-002-1; 02 NEBRASKA
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
IA FULLY EXECUTED/ON SCHEDULE
Project under construction
Typical: 12–24 months
Proposed COD: 2024-06-28
SPP-GEN-2016-147 is a proposed 40 MW solar generation project located in Cheyenne County, Nebraska. The development project is listed in the interconnection queue of the Southwest Power Pool (SPP), with Tri-State identified as the associated utility. No developer name is given in the queue data. The project would connect to the grid at the Sidney 115 kV Substation and has requested Energy Resource Interconnection Service (ERIS).
The project entered the SPP queue on November 30, 2016, and was studied as part of the DISIS-2016-002-1 cluster in the 02 Nebraska study group. Its queue status is active, and an interconnection agreement (IA) has been executed. The proposed commercial operation date was June 28, 2024.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NE
County
Cheyenne
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
Tri-State
Entity
SPP
Service Type
ERIS
Point of Interconnection
Sidney 115 kV Sub
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- SCSE
- POI Substation
- Sidney Tri-State Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project SPP-GEN-2016-147Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.