SPP-GEN-2016-111
302 MW generation in Mcpherson, KS · In queue since November 2016 · Proposed COD January 2027
302 MW
Capacity
1
Components
Wind
9y 11m
In Queue
IA Executed
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
10y 2m
Study Phase
DISIS-2016-002-1; 03 CENTRAL
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
IA FULLY EXECUTED/ON SCHEDULE
Project under construction
Typical: 18–36 months
Proposed COD: 2027-01-15
SPP-GEN-2016-111 is a proposed 302 MW wind generation project located in McPherson County, Kansas, within the Southwest Power Pool (SPP) region. The development project consists of a single wind component totaling 302 MW. No project name or developer is identified in the interconnection queue data. The associated transmission owner is listed as WERE, and the project is proposed to connect to the grid at the Reno – Summit 345 kV point of interconnection.
The project entered the SPP interconnection queue on November 30, 2016, and holds an active status. It was evaluated as part of the DISIS-2016-002-1 cluster study within the 03 Central study area, and has requested Energy Resource Interconnection Service (ERIS). An interconnection agreement has been executed for the project, which has a proposed commercial operation date of January 15, 2027.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
KS
County
Mcpherson
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
WERE
Entity
SPP
Service Type
ERIS
Point of Interconnection
Reno - Summit 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- POI Substation
- SUMMIT
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project SPP-GEN-2016-111Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.