SPP-GEN-2016-074
200 MW generation in Custer, NE · In queue since April 2016 · Proposed COD July 2027
200 MW
Capacity
1
Components
Wind
10y 6m
In Queue
IA Executed
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
11y 3m
Study Phase
DISIS-2016-002-1; 02 NEBRASKA
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
IA FULLY EXECUTED/ON SCHEDULE
Project under construction
Typical: 18–36 months
Proposed COD: 2027-07-01
SPP-GEN-2016-074 is a proposed 200 MW wind generation project located in Custer County, Nebraska. The development project is listed in the interconnection queue of the Southwest Power Pool (SPP), with Nebraska Public Power District (NPPD) as the associated transmission utility. The project consists of a single wind component totaling 200 MW and is planned to connect to the grid at the Sweetwater 345 kV point of interconnection. No developer or project name has been disclosed in the available queue data.
The project entered the SPP interconnection queue on April 14, 2016, and remains in active status. It was studied as part of the DISIS-2016-002-1 cluster within the 02 Nebraska study group and has requested Energy Resource Interconnection Service (ERIS). An interconnection agreement has been executed for the project, and its proposed commercial operation date is July 1, 2027.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NE
County
Custer
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
NPPD
Entity
SPP
Service Type
ERIS
Point of Interconnection
Sweetwater 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- POI Substation
- Sweetwater Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project SPP-GEN-2016-074Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.