SPP-GEN-2015-071
200 MW generation in Beckham, OK · In queue since October 2015 · Proposed COD December 2021
200 MW
Capacity
1
Components
Wind
10y 9m
In Queue
Withdrawn
IA Phase
COD target: 2021
Total Duration
6y 2m
Schedule
55 months past proposed COD
Study Phase
DISIS-2015-002-7
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-12-31
SPP-GEN-2015-071 is a proposed wind generation project with a total capacity of 200 MW, located in Beckham County, Oklahoma. The project is in the Southwest Power Pool (SPP) interconnection queue, with an original queue entry date of October 9, 2015. The proposed commercial operation date was December 31, 2021. The interconnecting utility is AEP.
The interconnection agreement (IA) status for SPP-GEN-2015-071 is listed as Withdrawn. The point of interconnection (POI) is the Chisholm 345kV substation.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OK
County
Beckham
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
SPP
Service Type
ERIS
Point of Interconnection
Chisholm 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- POI Substation
- Chisholm Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project SPP-GEN-2015-071Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.