SPP-GEN-2015-055
40 MW generation in Beckham, OK · In queue since October 2015 · Proposed COD December 2024
40 MW
Capacity
1
Components
Solar
10y 9m
In Queue
Withdrawn
IA Phase
COD target: 2024
Total Duration
9y 2m
Schedule
20 months past proposed COD
Study Phase
DISIS-2015-002-7; 04 SOUTHEAST
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-01
SPP-GEN-2015-055 is a proposed 40 MW solar generation project located in Beckham County, Oklahoma. The project, under consideration in the Southwest Power Pool (SPP) interconnection queue, is being developed by Western Farmers Electric Cooperative (WFEC). The project entered the queue on October 6, 2015, with a proposed commercial operation date of December 1, 2024. The point of interconnection is the Erick 138kV Substation.
The interconnection agreement (IA) status for SPP-GEN-2015-055 is currently listed as Withdrawn.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OK
County
Beckham
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
WFEC
Entity
SPP
Service Type
ERIS
Point of Interconnection
Erick 138kV Substation
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project SPP-GEN-2015-055Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.