SPP-GEN-2015-030
200.1 MW generation in Noble, OK · In queue since March 2015 · Proposed COD November 2017
200.1 MW
Capacity
1
Components
Wind
11y 4m
In Queue
Withdrawn
IA Phase
COD target: 2017
Total Duration
2y 8m
Schedule
106 months past proposed COD
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2017-11-01
SPP-GEN-2015-030 is a proposed wind generation project with a total capacity of 200.1 MW. The project is located in Noble County, Oklahoma, and interconnects within the Southwest Power Pool (SPP) region to Oklahoma Gas & Electric (OGE) at the Sooner 345kV point of interconnection. The project entered the SPP interconnection queue on March 19, 2015, with a proposed commercial operation date of November 1, 2017.
The interconnection agreement (IA) status for SPP-GEN-2015-030 is listed as Withdrawn.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OK
County
Noble
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
OGE
Entity
SPP
Service Type
ERIS
Point of Interconnection
Sooner 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- OKGESO1
- POI Substation
- Sooner Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project SPP-GEN-2015-030Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.